Career Spot 77: JumboTests Updates: Updated: Question in GATE 2012 Mining Engineering Paper with Solution

Career Spot 77
Career News.....www.careerspot77.koolcentre.in,movies news.....www.koolcentre.in
JumboTests Updates: Updated: Question in GATE 2012 Mining Engineering Paper with Solution
Aug 7th 2012, 09:10

JumboTests Updates
Score Big with jumbotests.com! The site is regularly updated & improved. This feed keeps you up to date on the changes & additions to as they happen.
Updated: Question in GATE 2012 Mining Engineering Paper with Solution
Aug 7th 2012, 08:55

A question in GATE 2012 Mining Engineering Paper with Solution has been updated:

Common Data for Questions 50 and 51: The following data are provided for a surface mine to be excavated by a shovel:

Production target : 10000 te/shift
Available hours per shift : 6 hrs
Shovel loading cycles per hour : 106
Bank density of the material mined : 2400 kg/m3
Swing factor at 1200 swing : 0.91
Bucket fill factor : 0.64
Utilization of available time : 83%
No of working days in a year : 300
No of shifts per day : 3

The annual production target in Mte is

  1. 5.76
  2. 7.00
  3. 8.19
  4. 9.00

You are receiving this email because you subscribed to this feed at blogtrottr.com. If you no longer wish to receive these emails, you can unsubscribe from this feed, or manage all your subscriptions

You are receiving this email because you subscribed to this feed at blogtrottr.com.

If you no longer wish to receive these emails, you can unsubscribe from this feed, or manage all your subscriptions

No comments:

Post a Comment